Since the last project meeting we've slipped the 3.0 release schedule. I'm proposing the following schedule for the 3.0 release:
- 3.0.0 feature freeze and beta release - 2011-12-17
- (...bug fixing...)
- 3.0.0 RC1 release (0 open bugs for release) - 2011-12-31
- 3.0.0 RC N - every week or so as needed for critical bugs only
- 3.0.0 release - January 2012
Eric Davis
Okay, I'm going to feature freeze 3.0.0 now and get 3.0.0 beta ready to be released this weekend.